3, 4, and 5 year old preschool openings at the United Christian Academy in Smethport, PA. Transportation provided. Open house and registration on Friday, April 25th from 2-4 p.m. and 6-8 p.m. Only $60.00 per month for 2 mornings per week. Applications available at the school office by calling 814-887-9231. Also accepting enrollment for kindergarten through 12th grade for the 2014-15 school year. The school offers developmental screening for preschoolers and employs only PA certified teachers.........................What do bugs, candy, rollercoasters, and legos have in common? They are all things that your kids could be doing this summer instead of just watching TV or playing video games. Send them to the half day summer camp program at the United Christian Academy in Smethport, PA. They will participate in special theme weeks which include many different activities, as well as a summer-long Olympics competition complete with medals and award ceremony. Call the school at 814-887-9231 for an application. Only $50.00 per week for a great learning experience. 9 a.m. to noon

Tuesday, November 6, 2012

PennDOT Plans to Open New Dry Run Bridge on Route 477 Friday

PennDOT Plans to Open New Dry Run Bridge on Route 477 Friday

Lock Haven –PennDOT plans to open the new Dry Run Bridge on Route 477 by the end of the day, Friday. Work has been underway since early April to replace the 75-year old bridge, which spans Dry Run in Lamar Township, about a half mile east of Salona. Replacing the old bridge will allow PennDOT to remove it from the list of structurally deficient bridges in Clinton County.

Once the bridge is open, PennDOT will be able to lift the detour that’s been in place since early June. The 7-mile detour used Route 477, Route 220, and Route 2008 (Auction Road).

Remaining work on the project will be done during daylight hours with traffic control. Area drivers could encounter flaggers in the roadway until Thanksgiving, as workers finish up the project.

Work on the bridge has included full structure replacement, waterline relocation, guide rail and drainage updates, paving of approaches and miscellaneous construction.

All work is weather and schedule dependent. LTT Trucking of North Bend has been the contractor on this $1 million project. Drivers are reminded to be cautious in all work zones and always buckle up.