...WINTER STORM WARNING REMAINS IN EFFECT FROM 1 PM THIS AFTERNOON TO 10 AM EST TUESDAY... * ACCUMULATIONS...6 TO 10 INCHES OF SNOW. * TIMING...RAIN WILL BECOME MORE STEADY THIS MORNING BEFORE MIXING WITH AND CHANGING TO SNOW THIS AFTERNOON. SNOW WILL FALL HEAVY AT TIMES INTO THE EVENING HOURS BEFORE TAPERING TO LIGHT SNOW AND SNOW SHOWERS AFTER MIDNIGHT. * IMPACTS...SNOW ACCUMULATIONS WILL MAKE TRAVEL VERY HAZARDOUS. THE WEIGHT OF THE HEAVY WET SNOW COULD CAUSE TREE LIMBS TO FALL ON POWER LINES AND PRODUCE OUTAGES. * WINDS...NORTHEAST 5 TO 15 MPH WITH GUSTS UP TO 30 MPH. * TEMPERATURES...IN THE MID 30S. * GREATEST RISK FOR HEAVY SNOW IN THE HIGHER ELEVATIONS. * LONGER COMMUTE TIMES MONDAY EVENING.

Tuesday, August 9, 2016

Construction to Begin on McKean County Bridge Project

Sullivan Road Bridge to be replaced as part of Public-Private Partnership

Clearfield, PA – The Pennsylvania Department of Transportation’s (PennDOT) Rapid Bridge Replacement Project continues in McKean County in August with the reconstruction of a bridge in Bradford Township. Replacement of this bridge will allow PennDOT to remove it from McKean County’s list of structurally deficient bridges.

The bridge (JV-73) spans Bennett Brook on Route 4011 (Sullivan Road). Construction is expected to start during the week of August 22 and be complete in November. During this time, drivers will be directed to follow a detour along Route 4009 (Interstate Parkway).

In the event of unfavorable weather or unforeseen activities, this schedule may change.
This bridge replacement is part of the Rapid Bridge Replacement Project, a Public-Private Partnership (P3) between PennDOT and Plenary Walsh Keystone Partners (PWKP) under which PWKP will finance, design, replace and maintain the bridges for 25 years. The P3 approach will allow PennDOT to replace the bridges more quickly while achieving significant savings and minimizing impact on motorists.

To see the bridges included in the statewide initiative and to learn more about the Rapid Bridge Replacement Project and P3 in Pennsylvania, visit www.P3forPA.pa.gov. Additional information on the project, the team and how to bid on the project can be found at www.PARapidBridges.com.