BRADFORD BYPASS PROJECT MID-WEEK UPDATE

CLEARFIELD – The Pennsylvania Department of Transportation (PennDOT/District 2) issues the following mid-week update (April 15 – 18) for the Route 219, McKean County/Bradford Bypass project. Contractor on the $28.1 million project is Glenn O. Hawbaker, Inc. The project extends from just north of the city of Bradford in Pennsylvania to the New York State line.
All work is weather and schedule dependent and can be subject to change.

The following work schedule is for April 15 — 18:
• Route 219 southbound is restricted to one lane from one mile north of the state line (in New York State) to the Forman Street off-ramp. Traffic will be using the existing travel lane.
• Contractor will set temporary barrier in preparation for crossover construction.
• Contractor will be working on emergency pull-offs on the northbound lanes.
• Access to Hillside Drive from the north (southbound traffic) will be eliminated on Thursday (4/16). Traffic is to follow the posted detour.
• Extra caution should be taken while entering the construction area from the on-ramp areas. Be aware of approaching traffic speeds and restricted lanes at ramps.
• All ramps remain open.
• Motorists need to watch for slow moving and stopped vehicles through the entire work zone.
• Please obey posted speed limits and remember to always buckle up.

For more information on roadway construction and maintenance operations, visit PennDOT’s website at www.dot.state.pa.us.