Friday, May 22, 2009

BRADFORD BYPASS PROJECT UPDATE, WEEK OF MAY 25

CLEARFIELD – The Pennsylvania Department of Transportation (PennDOT/District 2) issues the following update for the Route 219, McKean County/Bradford Bypass project. This update is for the week of May 25. Contractor on the $28.1 million project is Glenn O. Hawbaker, Inc. The project extends from just north of the city of Bradford in Pennsylvania to the New York State line.

All work is weather and schedule dependent and can be subject to change. The contractor will not work on Monday, May 25 in observance of the Memorial Day Holiday. The following work schedule is for the week of May 25:

• Northbound and southbound traffic are traveling in the northbound lanes, separated by concrete barrier from Forman Street to north of Hillside Drive.
• Southbound ramps at the Foster Brook interchange are closed. Traffic is to follow the posted detour.
• Contractor is working on southbound reconstruction by removing existing roadway from the New York state line heading south.
• Contractor is working on southbound bridges. Work includes expansion dam replacements, steel retrofits and deck repairs.
• Tuna Crossroads remains closed for bridge demolition. Traffic is to follow the posted detour.
• Tuna Valley Trail access at Bolivar Drive is closed due to bridge work. Trail access is still available at Crook Farms and the Seaward Avenue side of Tuna Crossroads (Township Route 369).
• Access at Hillside Drive is restricted from Route 219 north to Hillside Drive and from Hillside Drive to Route 219 south. Traffic is to follow the posted detour.
• Drivers should use extra caution while entering the construction area from the on-ramp areas. Be aware of approaching traffic speeds and restricted lanes at ramps.
• Motorists need to watch for slow moving and stopped vehicles through the entire work zone.
• Lane width in the construction zone is 10 feet.
• Please obey posted speed limits and remember to always buckle up.

For more information on roadway construction and maintenance operations, visit PennDOT’s website at www.dot.state.pa.us.