BRADFORD BYPASS PROJECT UPDATE, WEEK OF JUNE 29

CLEARFIELD – The Pennsylvania Department of Transportation (PennDOT/District 2) issues the following update for the Route 219, McKean County/Bradford Bypass project. This update is for the week of June 29. Contractor on the $28.1 million project is Glenn O. Hawbaker, Inc. The project extends from just north of the city of Bradford in Pennsylvania to the New York State line.

All work is weather and schedule dependent and can be subject to change. The following work schedule is for the week of June 29:

• The work zone will remain in place over the July 4 holiday. The contractor plans to work on July 3 and July 6 at Kendall Avenue and on Route 219, July 6.
• Kendall Avenue southbound remains closed for reconstruction. Kendall Avenue is restricted to one lane for northbound traffic only. Southbound traffic is to follow the posted detour. Kendall Avenue work includes sub-grade repairs, sub-base placement, concrete placement and drainage updates.
• Contractor is working on southbound reconstruction by performing sub grade repairs and drainage work.
• Northbound and southbound traffic are traveling in the northbound lanes, separated by concrete barrier from Forman Street to north of Hillside Drive.
• Southbound ramps at the Foster Brook interchange remain closed. Traffic is to follow the posted detour.
• Contractor is working on southbound bridges. Work includes expansion dam replacements, steel retrofits, deck repairs and painting.
• Tuna Crossroads (Township Route 369) will be opened until beams are set later this year.
• Tuna Valley Trail access at Bolivar Drive is closed due to bridgework. Trail access is still available at Crook Farms and the Seaward Avenue side of Tuna Crossroads (Township Route 369).
• Access at Hillside Drive is restricted from Route 219 north to Hillside Drive and from Hillside Drive to Route 219 south. Traffic is to follow the posted detour.
• Drivers should use extra caution while entering the construction area from the on-ramp areas. Be aware of approaching traffic speeds and restricted lanes at ramps.
• Motorists need to watch for slow moving and stopped vehicles through the entire work zone.
• Lane width in the construction zone is 10 feet.
• Please obey posted speed limits and remember to always buckle up.