Update for Bradford Bypass Project for Week of Nov. 8

Update for Bradford Bypass Project for Week of Nov. 8

Clearfield – All lanes are expected to be open on Thursday, Nov. 11 on PennDOT’s Route 219/Bradford Bypass project in McKean County. All work is weather and schedule dependent. PennDOT issues the following travel update for the week of Nov. 8. Glenn O. Hawbaker, Inc. of State College is the contractor on this $28 million job.

• Motorists are advised to watch for slow-moving and stopped vehicles throughout the entire work zone.


• The southbound and northbound lanes of Route 219 from Elm Street to Hillside Drive in New York State will be restricted to one lane in each direction. The passing (left) lanes will be closed for media work. All ramps are open. Lane restrictions are expected to be removed on Thursday, Nov. 11.


• Work on the Route 219 southbound ON-ramp at Elm Street continues. Traffic will continue to use the existing shoulder. The contractor crew will be working close to the roadway placing plants behind the new barrier wall. Expect delays during work hours.

• Access at Hillside Drive is restricted from Route 219 south to Hillside Drive and from Hillside Drive to Route 219 south. Access at Hillside Drive is expected to be open on Thursday, Nov. 11.

• The contractor will be working close to the travel lanes, building an emergency crossover, placing paint lines, delineation, signs and right-of-way fence. Watch for workers and equipment being close to the travel lanes.