UPDATE FOR ROUTE 255 BETTERMENT WORK NEAR I-80/DUBOIS, WEEK OF JUNE 17

UPDATE FOR ROUTE 255 BETTERMENT WORK NEAR I-80/DUBOIS, WEEK OF JUNE 17

Update for Route 255 Betterment Work near I-80/DuBois Continues

DuBois - Work to improve Route 255 near the Interstate 80 DuBois/101
interchange that began in April is continuing. When work completes in
mid-October, a smoother roadway surface and new traffic signals at the I-80
ramps will provide area drivers with more efficient travel and improved
traffic flow.

Work this week will include cutting and patching work on Route 255 starting
Monday. Subcontractor Plum Contracting Inc. of Greensburg will begin
working on the drainage on the roadway shoulders from Treasure Lake to the Fairfield
Inn on Wednesday. The cutting work is expected to wrap up by Friday, June 21,
while the shoulder drain work will take approximately three weeks.

Subcontractor Kukurin Contracting Inc. of Export will continue drilling and
placing a new water line in the area next week.

Motorists can expect to encounter flaggers in the work zone and travel
delays. Drivers should give themselves extra time to travel through the area.

PennDOT reminds drivers to remain alert and proceed through the work zone with
caution.

All work is weather and schedule dependent. Work is scheduled to end by
mid-October of this year. New Enterprise Stone and Lime Inc. is the
contractor on this $3.4 million project.