Update for Route 255 Project in Saint Marys, Week of March 24

Update for Route 255 Project in Saint Marys, Week of March 24

Saint Marys – Work to improve a section of Route 255 in the city of Saint Marys is continuing as spring begins. The project stretches from the Tractor Supply Co. intersection to Route 120/State Street in Saint Marys. Once the project completes in late summer 2014, travel along this section of Route 255 will be smoother and more efficient.

Activity the week of March 24 will include:

• The contractor will begin work on Monday morning at 7 a.m. and continue through Thursday. All work will be performed during daytime hours.

• Route 255 northbound will be restricted to one lane between Pistner Road and Iron Run Road so that work on the access road can take place.

• Route 255 will continue to be restricted to one lane northbound and one lane southbound between Vine Street and State Street for the installation of sanitary sewer lines and water lines.

• Vine Street will remain closed between South Saint Marys Street (Route 255) and Chestnut Street. Motorists are to follow the signed detour route. This portion of Vine Street will remain closed until further notice. The closure is required for the installation of a water line and a sanitary sewer line.

• The contractor will be working on traffic signals between the Tractor Supply intersection and Plaza Drive.

All work is weather and schedule dependent. Motorists are advised to watch for slow-moving and stopped vehicles through the entire work zone. Motorists are advised to be cautious when traveling through the work zone and to obey the posted speed limit.

Overall work includes pavement repair, drainage improvements, addition of a right-turn lane for Route 255 northbound traffic at Vine Street, re-alignment of the Arch Street intersection, a right turn lane on Route 120 east for traffic heading south on Route 255, and other construction items. Dave Gutelius Excavating Inc. of Mifflinburg is the contractor on this $12.8 million project.