I-80 WB resurfacing project in Columbia County continues

I-80 WB resurfacing project in Columbia County continues

On Sunday night, July 13, work will continue on a $2.6 million resurfacing project in Interstate 80 westbound in Columbia County.

The work includes milling and paving five miles in both lanes from Fishing Creek Bridge to the Montour County line.

Prime contractor Glenn O. Hawbaker, Inc., will begin at Fishing Creek Bridge, approximately 0.5 miles east of the Buckhorn interchange (Exit 232), and work toward the Montour County line in the passing lane using two 12-hour shifts and working non-stop from Sunday evenings at 7 p.m. to Fridays at noon.

Two lanes will be open to traffic from Friday to Sunday night. Traffic will be reduced to one lane while the work is being performed but all on ramps and off ramps at the Buckhorn interchange will remain open.

Motorists are advised to expect delays, proceed carefully through the work zone, be aware of changing traffic patterns and most importantly, watch for workers in the construction zone.

The contractor is on an aggressive work schedule to limit the duration of impact to motorists. Weather permitting, the paving is expected to be completed within three weeks. The entire project is scheduled to be completed Aug. 22.